How should a data-centre generator be maintained?
A data-centre generator is maintained with a monthly exercise under real load, an annual run at higher load when the monthly runs fall short, and a preventive visit that covers the engine, the fuel and the controls. NFPA 110 sets the US benchmark of 30 minutes at not less than 30 percent of nameplate each month; in Canada, CSA C282 governs emergency generators. The UPS is part of the same test: it has to accept the generator and hand the load to it.
Need the UPS in this room serviced? Get a quote
On this page
Key facts
- Monthly exercise:
- At least 30 minutes at not less than 30 percent of nameplate kW (via Cummins)
- Annual supplemental run:
- 50 percent for 30 minutes, then 75 percent for 1 hour, at least 1.5 hours in total Cummins
- CSA C282:
- Covers design, installation, operation, maintenance and testing of emergency generators in Canada CSA Group
- Wet stacking:
- Engines run below 30% for long periods cannot burn fuel completely (Kohler)
- Transfer switches:
- Operated monthly under the same standard Cummins
The monthly exercise
Short answer
The monthly exercise is a run of at least 30 minutes under enough load to bring the engine up to temperature. NFPA 110, as reprinted by Cummins, requires generator sets in service to be exercised at least once monthly for a minimum of 30 minutes, either at a load that keeps the exhaust gas temperature at the maker's minimum or at not less than 30 percent of the nameplate kW rating. Starting the engine and letting it idle does not meet either test. The run also proves the start sequence, the batteries that crank the engine, and the transfer switch, which NFPA 110 requires to be operated monthly.
When the building load is too small
When the building load is too small, an annual run with supplemental load makes up the difference. Under NFPA 110 as reprinted by Cummins, a diesel installation that cannot meet the monthly requirement is exercised monthly with the load it has, and annually with supplemental load at not less than 50 percent of nameplate for 30 continuous minutes and not less than 75 percent for 1 continuous hour, a total of at least 1.5 hours. In data centres the gap is common. Kohler notes that generators were historically greatly oversized for the usual load, and that because operators do not want to move the IT load onto the generator for a test, the monthly exercise uses a load bank; see generator load bank testing for how that test is connected and run.
Wet stacking
Wet stacking is unburned fuel collecting in the exhaust of a diesel that runs too lightly. Kohler explains that when generators run at less than 30% of capacity for long periods, the engine cannot reach the temperature needed to burn fuel completely. Generac describes the result: liquid diesel passes into the exhaust, seen as black smoke and oily residue in the stack, and puts the exhaust temperature needed for aftertreatment at a minimum of about 536°F (280°C), reached at roughly 30% load as a rule of thumb. Cummins' NFPA 110 summary advises minimizing operation below 30% load. Light monthly runs are the usual cause, which is why the annual load run exists.
The preventive maintenance visit
- Engine: oil and filters, coolant level and condition, belts and hoses, and leaks
- Fuel: tank level, water and sediment, and fuel condition for stored diesel
- Starting system: cranking batteries, charger and connections
- Air intake and exhaust: filters, restrictions and signs of wet stacking
- Controls and alarms: settings, event logs and the remote start signal
- A test run under load, with voltage, frequency and temperatures recorded
The intervals for each item come from the engine maker and from the standard that applies to the site. NFPA 110 also sets a longer test for Level 1 systems: at least once within every 36 months, for the assigned class duration, with the test allowed to stop at 4 hours where the class is longer.
The standard in Canada
In Canada, CSA C282 applies to emergency generators. CSA describes C282 as covering the design, installation, operation, maintenance and testing of generator sets and associated equipment supplying emergency power where the National Building Code of Canada requires it, and its current edition sets the minimum load for monthly testing at 30%. C282 does not cover emergency power from storage batteries or a UPS, so the UPS is maintained under its maker's instructions and the switchgear standards. Many data-centre generators are standby rather than code-required emergency supply; even then, C282 and NFPA 110 are the usual benchmarks for the test programme.
Testing the generator with the UPS
The generator and the UPS are tested together by transferring real load and watching the UPS accept the generator. Cummins notes that without a UPS the load is lost for approximately 10 seconds while the generator starts and the transfer switch moves; with a UPS, the battery covers that gap, and the question becomes whether the UPS accepts the generator's voltage and frequency.
Eaton warns that a generator whose frequency swings outside the UPS input window can leave the UPS on battery until the battery runs out. Cummins recommends using a UPS's generator mode if it has one, and notes that a UPS with walk-in lets the battery take the load first and ramps it onto the generator. A periodic integrated test, with the IT load protected, proves the whole chain, and a meter on the UPS input during the run shows how the two interact (see power quality and harmonics); the UPS and generator compatibility guide covers the settings.
Several generators
A data centre often runs several generators. Kohler notes that a typical data-centre facility uses between five and ten generators, and that load bank exercising for all of them adds up to a significant time commitment for operations staff. Generator maintenance is therefore planned as a programme rather than one visit at a time, with the monthly runs, the annual load runs and the integrated tests on one calendar alongside the UPS preventive maintenance schedule.
Quoting with the UPS
Generator service is delivered through specialist partners and quoted alongside the UPS and transfer switch work, so the monthly runs, the annual load bank run and the integrated test are on one plan. Send the generator make, rating and fuel type through the quote request form.
Questions
How often should a standby generator be run?
At least once a month for at least 30 minutes, at not less than 30 percent of nameplate kW or at the maker's minimum exhaust temperature, under NFPA 110 as reprinted by Cummins.
What is an annual generator load bank test?
A run with supplemental load at not less than 50 percent of nameplate for 30 minutes and 75 percent for 1 hour, for sites whose monthly runs do not reach the required load.
What is wet stacking?
Unburned diesel collecting in the exhaust of an engine run too lightly; Kohler ties it to long periods below 30% of capacity.
Does CSA C282 cover the UPS?
No. CSA C282 covers generator sets supplying emergency power and does not cover emergency power from storage batteries or a UPS.
Sources, checked 2026-10-04:
- Reference Cummins, NFPA 110 Testing and Service Requirements for Standby Power Systems (PowerHour, 15 Dec 2020), reprinting NFPA 110-2016, p. 29-43
- Standard CSA Group, CSA C282:24 Emergency electrical power supply for buildings (product page: preface and scope)
- Reference Kohler Power Systems, Data Center Generator Maintenance: Feasibility and Benefits of No-Load Exercising (Power Systems Topics 130), p. 1-2
- White paper Generac, Wet Stacking Mitigation Technologies (white paper, A. LaCroix), p. 1
- Reference Cummins, Specifying standby generator set requirements for data centers (PowerHour, 10 Aug 2022)
- White paper Cummins, Specifying the right transfer switch (white paper, H. Obeid)
- Reference Eaton, Six considerations to achieving generator-UPS harmony