Skip to content
1 (438) 800-0382FR FrançaisGet a quote

Load bank testing

Load bank test procedure and requirements

A load bank test puts an uninterruptible power supply (UPS) under a controlled, measured load to check that it meets its own specification at known load steps and through transfers. The method is written before the visit: site checks, connections by a certified electrician, 50% then 100% load, a short battery discharge, repeated transfers and a report.

Fig. 1 · Load steps and hold times

Load steps and hold timesA step chart of load on the UPS output against time: 50% load held for one hour, then 100% load held for three hours.Load on the UPS outputTime50%one hour100%three hoursThen: battery discharge, repeated transfers, loadremoved.
Load steps from Eaton's UPS load bank procedure; the maker's method for each model sets its own. Source: Eaton, Load Bank Testing Scope of Work (Attachment L-6)

Key facts

First check:
The electrical infrastructure can carry the critical load and the load bank's artificial load at the same time Eaton
Sign-off before testing:
Approval from the electrician and/or site personnel, based on that check Eaton
Connections:
Made by a certified electrician, with the UPS locked out where applicable Eaton
Heat:
Load bank placed where heat can be rejected safely; 50 feet of cable in Eaton's scope, more on request
Load steps:
50% for one hour, then 100% for 3 hours Eaton
Load bank listing:
UL 508A, CSA or CE marking ASCO Power Technologies

What does a load bank test prove?

Short answer

It proves the UPS meets its own specification under a known load: Vertiv describes load bank tests as a way of validating the correct operational performance of the overall system. For a UPS, ASCO puts the point plainly: what matters is its ability to perform at differing power outputs, and for how long. A load bank supplies that load in steps that can be accurately controlled, measured and recorded, while the critical load runs on maintenance bypass, on utility power without UPS conditioning.

It does not prove battery runtime: the discharge in Eaton's method lasts up to 4 minutes, so runtime needs a separate capacity test; see UPS and battery load bank testing. Eaton also notes that all checks and processes may not be applicable to all equipment models: the method for the model on site decides.

Some large UPS offer an alternative. Vertiv's safe capacity test sends power in a closed loop from the inverter back to the rectifier through the static bypass, so the rectifier, inverter, contactors, fuses, power busses, cabling, bypass static switch, magnetics and filter capacitors are tested without an external load. With double-conversion efficiency above 96%, less than 4% of the circulating power is dissipated. Vertiv offers it on the Liebert Trinergy Cube and Liebert EXL S1, at load steps such as 25%, 50%, 75% and 100% and up to a 120% overload; a battery discharge in that mode needs energy fed back to the utility, which the site must clear with the utility supplier first.

Stages and records

  1. What happensInfrastructure check: the site can carry the critical load and the test load together
    What is recordedThe check, and the approval to proceed
  2. What happensCritical load transferred to bypass, then to maintenance bypass
    What is recordedTransfer times and any alarms
  3. What happensUPS modules shut down; lockout tag-out
    What is recordedWho applied the locks
  4. What happensLoad bank connected to the UPS output by the electrician
    What is recordedConnection points and cable route
  5. What happensUPS restarted and transferred to normal, on the load bank
    What is recordedUPS status and alarm log
  6. What happensLoad at 50% for one hour
    What is recordedVoltage, current, regulationinfrared and power-quality readings in a performance test
  7. What happensLoad at 100% for 3 hours
    What is recordedThe same readings, at full load
  8. What happensBattery discharge by opening the rectifier input, up to 4 minutes
    What is recordedUPS parameters during the dischargebattery cabinet scan
  9. What happensRectifier input restored; batteries recharge
    What is recordedRecharge behaviour
  10. What happensTransfers to bypass and back, repeated three times
    What is recordedWhether each transfer was clean
  11. What happensLoad removed, load bank isolated and disconnected, locks removed
    What is recordedCompletion of each step
  12. What happensCritical load returned from maintenance bypass to normal
    What is recordedFinal UPS statusthe report follows

Site requirements

The site must carry the extra load, give the load bank somewhere to shed its heat, and have a qualified person make the connections:

  • Capacity for two loads at once: the critical load stays on the bypass path while the load bank draws its test load from the UPS, so the upstream infrastructure must carry both. This is the first step of Eaton's method, and testing proceeds only once the electrician or site personnel approve it.
  • A place for the heat: a load bank turns its full test load into heat. It goes where that heat can be dissipated away from sensitive equipment, with cable run to it; Eaton's scope provides 50 feet and adds more on request.
  • A route in: portable units are built to fit through a man door or a freight elevator, but the route still needs checking.
  • Bypass and isolation: a maintenance bypass that can carry the critical load, and lockout tag-out of the UPS before connections are made.
  • A certified electrician: for the connections from the load bank to the UPS, before testing and again to remove them.
  • A listed load bank: ASCO recommends UL 508A, CSA or CE marking.

Sign-off before the load is applied

The electrician and the site's own personnel sign off after the infrastructure check. Eaton's method makes this approval its second step: nothing is transferred until the people responsible for the site agree that it can carry both loads. The written method also names who can stop the test and what readings would make them stop it.

Repeated transfers

After the load steps and the battery discharge, Eaton's method transfers the UPS to bypass and back to normal and repeats the transfer three times, under the test load, before the load bank is removed. A transfer fault found here is repaired before an outage depends on the transfer.

Time on site

The test itself takes a full working day. The load steps alone take one hour at 50% and 3 hours at 100%; add the transfers to and from maintenance bypass, the connections, the battery discharge of up to 4 minutes and its recharge, and the repeated transfers. Some UPS need longer steps or more of them: the maker's method for that model decides.

Performance test readings

A performance test adds thermal and power-quality readings. Eaton's performance-test scope runs the same load steps with an infrared scan of the UPS and battery cabinets at each step and during the battery discharge, and a power-quality meter on the UPS output recording voltages, currents and harmonic content. Hot spots are recorded with their actual temperatures, and thermographs go into the written report.

Protection during the test

The critical load runs on maintenance bypass, which means utility power without UPS conditioning. On some UPS the batteries are not available in maintenance bypass, as Schneider Electric notes for the Galaxy VS. The test window is chosen with that in mind: away from known utility work and storms, and with the generator ready.

Resistive or reactive load bank for a UPS?

A resistive bank loads at unity (1.0) power factor and gives kW only, so it will not load to full nameplate kVA; full kVA testing needs a reactive bank. ASCO notes that the electronic and non-linear loads simulated by capacitive banks are typical of the UPS industry, and lists resistive/reactive banks as a good choice for testing UPS systems. In factory acceptance testing, Aggreko describes resistive and reactive load bank testing of generators and UPS at full load with both leading and lagging power factors, and uses the reactive load to test the synchronization of the back-up systems. Resistive and reactive banks compared.

Where does the load test sit in commissioning?

For a new data centre, Aggreko sets out five testing levels for the critical power and cooling plant:

  • Level 1, factory acceptance testing: before delivery; for instance, resistive and reactive load bank testing to ensure full-load performance.
  • Level 2, site acceptance testing: by the OEM and/or installing contractors, with full load test documentation, method statements and schematics.
  • Level 3, pre-functional testing: each device checked as installed, wired, torqued and meggered before energization, then taken through the OEM start-up.
  • Level 4, individual system testing: UPS modules, generators, PDUs and bus-bar systems tested for full functionality, which can include load burn-in, generally on load banks, or thermal imaging.
  • Level 5, integrated system testing: the site at full load as one system, power, cooling and IT together, through staged machinery failures and utility problems.

Aggreko's best practice for a new centre is load bank simulation at initial commissioning, then at least once a year as part of a comprehensive maintenance plan. ASCO also uses a load bank after the maintenance schedule or repairs, to verify the design and the functional capabilities of the power system.

Which safety rules apply in Canada?

CSA Z462, now in its sixth edition (2024), specifies requirements for workplace electrical safety. It is based on NFPA 70E and harmonized with the Canadian Electrical Code and CSA Z460 on lockout, and it is used with the provincial, territorial and federal regulations that govern the site. Points that bear on a load bank test:

  • criteria for identifying and training the qualified electrical workers who do hazardous work;
  • verifying the absence of voltage at each point of work;
  • energy thresholds for safety requirements around batteries and battery rooms or enclosures.

Vertiv notes that an external load bank creates a hazardous environment because of the many operations during cable connections. In Eaton's method a certified electrician makes the connections, with lockout tag-out of the UPS where applicable.

What should the report contain?

Eaton's method ends with a report to the customer documenting the test results; it does not list the contents. Following the method's steps, a report would cover:

  • The load steps applied, with the voltage, current and regulation observed.
  • In a performance test, infrared images of the UPS and battery cabinets with the actual temperatures of any hot spots (Eaton includes the thermographs in the written report), and the UPS output voltages, currents and harmonic content from a power-quality meter.
  • The UPS operating parameters monitored during the battery discharge.
  • The transfers to bypass and back, repeated three times.
  • Any irregularities noted, as Eaton's performance-test scope requires for the power-quality readings.

Load bank control software can add to this: ASCO describes PC-based control with transient-speed instrumentation and full data acquisition reporting with graphical displays.

Questions

Who writes the test procedure?

The procedure follows the UPS maker's method for that model; it is written and agreed with the site before the visit, including the stop criteria and who signs off each step.

Does the test need an electrician?

Yes. In Eaton's method a certified electrician makes the connections from the load bank to the UPS before testing and removes them afterwards.

How much cable does a load bank need?

Enough to reach a place where its heat can be rejected safely. Eaton's scope supplies 50 feet and adds more on request.

What if a reading is out of range?

The test stops at the step where it happened, the load returns to a safe state as the written method sets out, and the finding goes in the report.

How often should a UPS be load bank tested?

For a new data centre, Aggreko's best practice is load bank simulations at initial commissioning, then at least once a year as part of a comprehensive maintenance plan. ASCO also uses a load bank after maintenance or repairs to verify the power system.

Resistive or reactive bank for a UPS test?

A resistive bank tests kW at unity power factor only. Full kVA testing needs a reactive bank, and ASCO lists resistive/reactive banks as suited to UPS systems. The written method for the UPS sets the load type.

Sources, checked 2026-10-11:

Need a UPS serviced, tested or replaced?

Tell us the site, the UPS and the timing. We reply and quote within 4 business hours, or call 1 (438) 800-0382

Timing

We reply and quote within 4 business hours.

More details
Call 1 (438) 800-0382Get a quote