Skip to content
1 (438) 800-0382FR FrançaisGet a quote

Load bank testing

UPS and battery load bank testing

A UPS load bank test proves the power train at known load steps; a battery capacity test proves how long the batteries can carry the load. They answer different questions, and a data-centre UPS needs both, each on its own schedule.

Fig. 1 · The battery discharge inside a UPS load bank test

The battery discharge inside a UPS load bank testThe rectifier input is opened, so the battery string feeds the inverter and the load bank on the UPS output; the critical load stays on maintenance bypass, fed from the utility input.Utility inputRectifier input openedUPSRectifierInverterBatterystringLoad bankDischarge path, up to 4 minutesMaintenance bypassCritical load
  • Under test
  • Battery and critical load
Opening the rectifier input puts the batteries on the load bank for a few minutes: it shows the transfer, not the runtime. Source: Eaton, Load Bank Testing Scope of Work (Attachment L-6)

Key facts

UPS load steps:
50% for one hour, then 100% for 3 hours, in Eaton's UPS load bank method
Battery discharge in that test:
Up to 4 minutes, by opening the rectifier input, then recharge Eaton
Readings during a performance test:
Infrared scans at each step and during the discharge; voltage, current and harmonics at the output Eaton
Runtime proof:
A battery capacity test, to the maker's procedure or the IEEE procedure it names EnerSys
Between capacity tests:
Internal ohmic readings at quarterly intervals, as IEEE-1188 recommends EnerSys
UPS that test themselves:
Liebert Trinergy Cube and EXL S1 (Vertiv safe capacity test), up to 120% load

What Does a UPS Load Bank Test Prove (and Not Prove)?

What the load bank test checks

Short answer

A UPS load bank test checks the power train under a known load: rectifier, inverter, static switch, contactors, controls and every connection between them, at the steps the method sets. In Eaton's method, voltage, current and regulation are watched at 50% load for one hour and at 100% load for 3 hours; its performance-test scope adds an infrared scan of the UPS and battery cabinets at each step and a power-quality meter on the output, recording voltages, currents and harmonic content. Hot spots are noted with their actual temperatures, so a connection that is starting to fail can be fixed before it does.

The short battery discharge

The short battery discharge shows that the batteries pick up the load cleanly and that the UPS behaves while they do. Eaton's method opens the rectifier input for a discharge of up to 4 minutes, monitors the UPS operating parameters, then restores the input and lets the batteries recharge; its performance version scans the battery cabinets with an infrared camera during the discharge. A few minutes on battery tests the transfer, the DC path and the connections, but not runtime.

Proving battery runtime

Runtime is proven by a capacity test: a controlled discharge at a defined rate until the batteries reach their end voltage, timed and compared with the rated value. EnerSys's VRLA manual gives its own capacity test procedure and points to the IEEE procedure as the alternative, and recommends internal ohmic measurements at quarterly intervals, following IEEE-1188, to track each block between capacity tests. The ohmic trend shows which blocks are drifting; the capacity test measures what the string delivers.

See battery replacement and testing for how the readings are taken and recorded, and the runtime calculator for a first estimate. When a string is due, battery modules for frames such as the Eaton 9PX are listed among these Eaton 9PX battery packs.

The critical load during the test

The critical load runs on the bypass path while the UPS output feeds the load bank. Eaton's method moves the critical load to bypass and then to maintenance bypass before shutting the UPS modules down, and the electrician connects the load bank to the output with the UPS locked out. On some UPS the batteries are not available while the unit is in maintenance bypass, as Schneider Electric notes for the Galaxy VS, so for the length of the test the load has utility power only. The window is therefore agreed in advance, and the infrastructure is checked to carry the critical load and the test load at the same time.

UPS that test themselves

Some large UPS can load their own power train. Vertiv's safe capacity test on the Liebert Trinergy Cube and the Liebert EXL S1 circulates power from the inverter back to the rectifier through the static bypass, so the power train runs at load with no external load bank; the engineer sets the load in steps up to an overload of 120%. Vertiv points out that an external load bank creates a hazardous environment through all the cable connections it needs, which the closed-loop test avoids. Its battery discharge mode back-feeds the utility, which must be accepted first.

Both tests in a maintenance plan

  • At commissioning: a load bank test of the UPS, and a capacity test of the new string as a baseline.
  • After a repair or module replacement: a load bank test to prove the work.
  • Every maintenance visit: ohmic readings, voltages and temperatures for each block, compared with the baseline.
  • When the trend says so: a capacity test, and a replacement plan if the string falls short.

For maintenance visits and contracts across Canada, see UPS battery repair and replacement service.

Questions

Does a UPS load bank test tell me my runtime?

No. Its battery discharge lasts minutes (up to 4 in Eaton's method). Runtime needs a capacity test to the battery maker's procedure.

How often should UPS batteries be tested?

EnerSys recommends internal ohmic readings at quarterly intervals, following IEEE-1188, with capacity tests when the trend or the maintenance programme calls for one.

Can the batteries be tested while the UPS protects the load?

Ohmic and voltage readings, yes. A capacity test discharges the string, so the load is protected another way during the test, and the plan says how.

What does the report include?

The load steps and readings, infrared findings with temperatures, power-quality readings at the output, UPS parameters during the battery discharge, the transfers, and the findings and recommendations.

Sources, checked 2026-10-04:

Need a UPS serviced, tested or replaced?

Tell us the site, the UPS and the timing. We reply and quote within 4 business hours, or call 1 (438) 800-0382

Timing

We reply and quote within 4 business hours.

More details
Call 1 (438) 800-0382Get a quote