Services
UPS installation and commissioning
Commissioning proves that a newly installed UPS works as designed before it carries the critical load: start-up to the maker's procedure, functional checks of every operating mode, a load test, battery checks, and a handover file with the results.

Equipment illustration
Installation and commissioning
Prepare a service request
Prepare a documented handover for a new or moved UPS.
Scope to confirm
Site checks, startup procedure, functional tests and acceptance records.
Have ready, if known
Model, electrical supply, room access, load and target commissioning date.
Send what you know. The equipment and access details can be confirmed after the first contact.
Key facts
- Start-up and warranty:
- Eaton defines product start-up as performed by an Eaton Customer Service Engineer or agent; parts warranty outside the U.S. runs 12 months from start-up or 18 months from shipment
- Permits in Ontario:
- Almost all electrical work needs a notification of work filed with the Electrical Safety Authority Electrical Safety Authority (Ontario)
- Load test steps:
- 50% load for one hour, then 100% for 3 hours, in Eaton's UPS load bank method
- Fresh batteries:
- A freshening charge and a float period before a load test, when the test falls within the maker's window (C&D)
4 h Reply and quote: within 4 business hours
Same day Same day: Montreal, Quebec City, Toronto, Ottawa
24 to 48 h Elsewhere in Canada: 24 to 48 hours
24/7 Emergency line: 24/7
How Is a New Data-Centre UPS Commissioned?
What commissioning proves
Short answer
Commissioning proves that the whole installed system does what the design says: the UPS starts, transfers, carries the load at its rating, runs on battery, returns to normal and raises its alarms. ASCO's load bank paper describes acceptance and commissioning testing as verifying that a new system will perform as designed, and for a UPS the question is its ability to perform at differing power outputs and for how long.
From delivery to handover
- What happensSite and drawing review before deliveryWhat is recordedClearances, ventilation, cabling and permit status
- What happensPlacement, cabling and battery installation checkedWhat is recordedTorque, polarity and installation checks
- What happensStart-up to the maker's procedureWhat is recordedSettings and start-up record
- What happensFunctional tests of every mode and transferWhat is recordedEach transfer and its result
- What happensAlarm and communication testsWhat is recordedAlarms received by the people who need them
- What happensLoad test at the maker's stepsWhat is recordedReadings at each stepany finding
- What happensBattery baseline readingsWhat is recordedPer-block reference values
- What happensHandoverWhat is recordedThe handover file and the maintenance schedule
Commissioning report
Report layout, example
| Step | % load | Duration | V | A | Hz | °C |
|---|---|---|---|---|---|---|
Report layout, example. Values are recorded on site.
- Installation: Clearances, cabling, torque and polarity checks
- Start-up: The settings and the start-up record, to the maker's procedure
- Tests: Each transfer and alarm test with its result, and the readings at each load step
- Handover: Battery baseline values per block and the maintenance schedule
Start-up and warranty
The maker's warranty decides who starts up a new UPS. Eaton, for example, defines start-up of its 93PM and 9395 families as performed by an Eaton Customer Service Engineer or agent, and starts the parts warranty from that date. Read the warranty terms before booking the installation, and plan commissioning around the approved start-up. Electrical work also needs its permits: in Ontario, the Electrical Safety Authority says almost all electrical work requires a notification of work.
Commissioning tests
- Pre-start checks: installation, cabling, torque, ventilation, clearances and the battery installation against the drawings and the manual.
- Start-up: to the maker's procedure, with settings recorded.
- Functional tests: each operating mode and transfer: normal, battery, static bypass, maintenance bypass, return.
- Alarm and communication tests: every alarm the site relies on, reaching the people who need it.
- Load test: the UPS at known load steps on a load bank, or with the UPS's own test function where the maker provides one.
- Battery baseline: readings on every block, as the reference for every later visit.
Load test on a new UPS
The load test puts the UPS output on a load bank before the critical load is connected, at the steps the maker's method sets; Eaton's UPS method runs 50% load for one hour and 100% for 3 hours, then a short battery discharge and repeated transfers. Some large UPS can test themselves: Vertiv's safe capacity test circulates power inside the Liebert Trinergy Cube and EXL S1 during start-up and commissioning, without an external load bank. New batteries need care before a discharge: C&D calls for a freshening charge and a float period before a load test within its stated window. The full method is under load bank testing.
Once every system on a new site has passed its own tests, the integrated systems test runs them together.
The handover file
- As-installed drawings and the equipment list with serial numbers.
- Start-up record and settings.
- Functional, alarm and load test results.
- Battery baseline readings for every block.
- Warranty terms, the start date and the maintenance schedule that keeps it valid.
- Open items and who closes them.
Installation across Canada
We install and commission three-phase UPS for data centres, server rooms and industrial sites, working to each maker's procedures and with the site's electrical contractor. For sizing before you buy, see UPS sizing; for installation and start-up, see UPS consultation, sales and installation.
Questions
Can commissioning be done without a load bank?
On some large UPS with a built-in test function, yes; otherwise a load bank is the way to prove the UPS at known load before it carries the critical load.
Does the warranty depend on the start-up?
Usually. Makers tie the warranty to an approved start-up; check the terms for your model before the installation date.
Do I need a permit to install a UPS?
Almost always for the electrical work. In Ontario, the Electrical Safety Authority requires a notification of work for almost all electrical work; other provinces have their own rules.
How long does commissioning take?
It depends on the size of the system and the tests in the method; a load test alone takes several hours.
Sources, checked 2026-10-04:
- Reference Eaton, 9315, 93PM and 9395 UPS family startup, warranty and support overview
- Reference Electrical Safety Authority (Ontario), Do I need to file a notification for electrical work?
- Reference Eaton, Load Bank Testing Scope of Work, Attachment L-6 (revised 5/12/2015), p. 1
- White paper Vertiv, Safe capacity test: Innovation and savings (white paper SL-70855, R09/22), p. 3-7
- Manual C&D Technologies, msEndur II VRLA batteries installation and operating manual RS02044/0418, p. 6-25
- White paper ASCO Power Technologies, Load Banks for Power System Testing (white paper, 2017), p. 2-6