Skip to content
1 (438) 800-0382FR FrançaisGet a quote

Guides

How do you size a UPS?

Size a UPS by adding up the load it must carry, in kW and kVA, adding margin for growth and inrush, then allowing for redundancy and runtime. Check the result against the generator, and confirm it with the maker's sizing data before ordering.

On this page
  1. Working out the load
  2. kW and kVA
  3. Other factors in the size
  4. The generator and UPS sizing
  5. Common sizing mistakes
  6. Redundancy from the start
  7. Sizing a replacement

Key facts

Basic method:
Volts times amps per device, summed, times 1.2 for growth (Eaton)
Inrush loads:
Motors, variable-speed drives, medical imaging and laser printers need extra VA (Eaton)
Power factor:
A unity output power factor UPS delivers more active power than a traditional 0.9 power factor UPS (Vertiv)
Unity example:
XPC M90U scales from 15 to 80 kW at unity power factor Xtreme Power Conversion
UPS range:
From as low as 300 VA to 5,000,000 VA or more (Eaton)
Planning horizon:
The next three to five years (Eaton)

How Do You Size a UPS for a Data-Centre Room?

Working out the load

Short answer

Work out the load from measurements where they exist, and from nameplates where they do not. Eaton's basic procedure: list every device the UPS will protect, find the volts and amps each draws, multiply for VA, add them up, and multiply by 1.2 for growth. Measured load from the existing UPS or the distribution is better than nameplate totals, which usually overstate it. Eaton adds that faster growth calls for a multiple above 1.2, and that new servers tend to draw more than the ones they replace.

Fig. 1 · kVA to kW at a power factor

kVA to kW at a power factorkW equals kVA times the output power factor. A 100 kVA UPS rated at 0.9 power factor carries at most 90 kW; a 100 kVA UPS rated at unity carries 100 kW.kW = kVA × power factor100 kVA UPS rated at 0.9 power factor100 kVA90 kW100 kVA UPS rated at unity100 kVA100 kWSame kVA rating, different kW capacity.
  • Apparent power (kVA)
  • Real power (kW)
Check the load in kW against the kW rating and in kVA against the kVA rating; both must fit.

kW and kVA

The UPS must carry both the load's real power (kW) and its apparent power (kVA). Older UPS were commonly rated at 0.9 output power factor, so a 100 kVA unit carried at most 90 kW; many current models are rated at unity. Vertiv notes that a unity power factor rating delivers more active power than a traditionally rated 0.9 power factor UPS, and XPC lists its M90U at unity, kW equal to kVA. Check the load in kW against the UPS's kW rating, not only kVA. For a model-by-model explanation, see the kW vs kVA reference for three-phase UPS.

Other factors in the size

  • Inrush: Eaton advises extra VA for motors, variable-speed drives, medical imaging and laser printers, which draw high current at start-up.
  • Growth: plan for the next three to five years, as Eaton suggests.
  • Redundancy: N+1 adds a module or unit beyond the load; 2N doubles the system. See N+1 and 2N.
  • Runtime: more runtime means more battery, not a bigger UPS, but the charger and the battery cabinets must suit it.

The generator and UPS sizing

The generator must carry the UPS input, including battery recharge, and hold voltage and frequency within the UPS's input window. Eaton's UPS basics paper suggests a generator of 1.5 to 3.0 times the UPS kVA rating, depending on the UPS design, alternator size, regulator type and fuel; its generator page gives 1.5 to 2 times the total load for UPS up to 25 kW, depending on fuel and governor. Cummins adds data-centre specifics, such as UPS rectifier harmonics and leading power factor from IT power supplies. Vertiv notes that a UPS with active input power factor correction avoids oversizing the generator; see UPS and generator compatibility.

Common sizing mistakes

The common mistakes are sizing on kVA alone and finding the kW short; sizing on nameplate totals and buying a UPS that runs at low load for years; and forgetting that redundancy only holds while the load fits in N. Running well below the rating costs efficiency, and running close to it leaves no room for growth, so the load is checked at every maintenance visit.

Redundancy from the start

Redundancy is easier to build in at sizing than to add later. N+1 needs one module or unit beyond the load; 2N needs a second complete system and path. Eaton's advice to estimate the next three to five years applies to both capacity and redundancy: a system that is N+1 today can drift to N as the load grows into the spare.

Sizing a replacement

We size replacements from the measured load, the growth plan and the redundancy design, and confirm with the maker's data before anything is ordered; see replacement planning. For installation and commissioning after sizing, see three-phase UPS installation for critical sites.

Browse the model library

Selected regional variants. Exact configuration and availability confirmed for each request.

Questions

How much margin should a UPS have?

Eaton's basic method multiplies the summed load by 1.2 for growth, more if fast growth is expected; plan for the next three to five years.

Should I size a UPS in kW or kVA?

Check both. Many current UPS are rated at unity power factor (kW equals kVA); older ones at 0.9. The load's kW must fit the UPS's kW rating.

Does more runtime need a bigger UPS?

Not usually: it needs more battery. The UPS's charger and battery cabinets must suit the larger battery.

How big should the generator be for a UPS?

Eaton suggests 1.5 to 3.0 times the UPS kVA, depending on the UPS design, alternator, regulator and fuel. Confirm with both makers.

Sources, checked 2026-10-04:

Need a UPS serviced, tested or replaced?

Tell us the site, the UPS and the timing. We reply and quote within 4 business hours, or call 1 (438) 800-0382

Timing

We reply and quote within 4 business hours.

More details
Call 1 (438) 800-0382Get a quote