Load bank testing

UPS load bank testing

A load bank test puts a controlled, measured load on a UPS so you can see how it holds its output at known load steps and through transfers, while the protected equipment stays on a separate path.

Equipment illustration

Key facts

What it validates:
That the UPS can meet its own specification, as a check of the whole system's operating performance Vertiv
Load steps in a published UPS method:
50% load for one hour, then 100% load for 3 hours Eaton
Battery check inside the test:
A battery discharge of up to 4 minutes, started by opening the rectifier input Eaton
Where the critical load sits:
On maintenance bypass, with the load bank connected to the UPS output Eaton
Readings during the test:
Infrared scan of UPS and battery cabinets; voltage, current and harmonic content at the output Eaton
The report:
Documents the test results Eaton

What the test proves

A load bank test proves that the UPS power train carries a known, steady load at each step and keeps its output in order while it does. Vertiv describes load bank tests as the usual way to confirm that a UPS meets its own specification and operates correctly as a system. Rectifier, inverter, static switch, contactors, busbars and connections all run warm at full load, which is when a weak joint or a worn component shows itself.

ASCO's load bank paper gives the reason for testing: the major reason a generator or UPS fails to perform is inadequate or improper maintenance, and after maintenance or repairs a load bank verifies the design and functional capability of the power system.

Fig. 1 · How a UPS load bank test runs

How a UPS load bank test runsSix steps in order: the critical load moves to maintenance bypass; the load bank is connected to the UPS output; the load is applied in steps, each held and read; a short battery discharge, then recharge; transfers to bypass and back, repeated; the load bank is removed and the load returns to the UPS. Steps three to five run under the test load.Critical load to maintenancebypassLoad bank connected to the UPSoutputLoad in steps, each held and readShort battery discharge, thenrechargeTransfers to bypass and back,repeatedLoad bank removed; load back onthe UPSTest load on
The sequence of Eaton's UPS load bank method; the critical load never sits on the UPS under test. Source: Eaton, Load Bank Testing Scope of Work (Attachment L-6)

The test sequence

The critical load is moved off the UPS first, then the load bank is connected to the UPS output and the load is applied in steps. In Eaton's published method for UPS load bank testing, the load goes to maintenance bypass, the UPS modules are shut down and locked out, an electrician connects the load bank to the output, and the UPS is restarted before any test load is applied. The load then runs at 50% for one hour and at 100% for 3 hours, with voltage, current and regulation watched throughout.

A short battery discharge follows (Eaton recommends up to 4 minutes, by opening the rectifier input), the batteries recharge, and the UPS is transferred to bypass and back several times before the load bank is removed and the critical load returns to normal. The full sequence, with what is recorded at each stage, is on the procedure and requirements page.

Stages of a UPS load bank test

  1. StageCritical load moved to maintenance bypass; UPS modules shut down and locked out
  2. StageLoad bank connected to the UPS output, UPS restarted
  3. StageTest load applied in steps, with voltage, current and regulation watched
  4. StageShort battery discharge, then recharge
  5. StageTransfers to bypass and back, load bank removed, critical load returned to normal

When to schedule a test

  • At acceptance or commissioning of a new or relocated UPS, before it carries the critical load, and in the integrated systems test that proves a new site as a whole.
  • After a repair or a major maintenance job, such as a capacitor, fan or power-module replacement, to prove the work under load.
  • Before a change that will lean on the UPS, such as a load increase, a generator change or a planned utility outage.
  • As part of a maintenance programme, when the UPS seldom runs near its rating and nobody has seen it carry full load.

ASCO calls a load bank the best practical means of proving a power system without interrupting critical loads.

What the report should show

The report should let someone who was not on site see what was tested, how, and what was found. Eaton's scope states that a report is provided documenting the results; its performance-test scope adds thermal and power-quality readings. Look for:

  • The load steps applied, their duration and the measured kW at each step.
  • Output voltage, current and regulation at each step, with any abnormality noted.
  • Infrared findings for the UPS and battery cabinets: hot spots, with the actual temperatures recorded.
  • Power-quality readings at the output: voltages, currents and harmonic content.
  • UPS parameters during the battery discharge, and the recharge.
  • The transfers to bypass and back, and whether each was clean.
  • Findings, open items and recommendations, with photos of anything that needs work.

Report layout, example

Site
UPS
Date
Method
Step% loadDurationVAHz°C
FindingsOKWatchAct

Report layout, example. Values are recorded on site.

Limits of the test

A load bank test does not prove battery runtime. The battery discharge inside a UPS load bank test lasts minutes, enough to show that the batteries pick up the load and that the UPS behaves while they do, but not how long they would carry it. Runtime is proven by a battery capacity test, for which battery makers point to the IEEE procedure, and tracked between tests with internal ohmic readings. See UPS and battery load bank testing for how the two fit together.

Nor does it test the distribution downstream of the UPS, or the generator. During the test the critical load runs on bypass, and on some UPS the batteries are not available while the unit is in maintenance bypass, as Schneider Electric notes for the Galaxy VS. The test window is therefore a period of reduced protection and is planned as one.

Testing without an external load bank

Some large UPS can be tested without an external load bank. Vertiv's safe capacity test on the Liebert Trinergy Cube and Liebert EXL S1 circulates power from the inverter back to the rectifier through the static bypass, so the power train is loaded without a load bank on the output. Vertiv states that with double-conversion efficiency above 96%, less than 4% of the circulating power is dissipated, and the test can run up to an overload of 120%. Its battery discharge mode back-feeds the utility, which the site must accept first.

The test plan

Every test follows a written method agreed before anyone arrives. The test plan sets whether the site's electrical infrastructure can carry the critical load and the test load at the same time, the bypass sequence, where the load bank and its cables go and where the heat is rejected, who signs off each step, and what happens if a reading is out of range. The report includes the load steps, the readings and the findings, written for whoever owns the UPS.

In this section

A load bank test

Prepare a service request

Scope to confirm

Connection point, load steps, hold times, transfers and recorded output readings.

Have ready, if known

UPS rating, single-line diagram, bypass arrangement and test window.

Send what you know. The equipment and access details can be confirmed after the first contact.

Get a quote for this work

Questions

How long does a UPS load bank test take?

In Eaton's published UPS method the load runs at 50% for one hour and at 100% for 3 hours, followed by a short battery discharge, recharge and repeated transfers. Add the time to move the load to bypass, connect and remove the load bank, so plan a working day.

Does the critical load stay powered during the test?

Yes, on the bypass path. The UPS is taken out of the load path and the load bank is connected to its output, so the test load never reaches the protected equipment. While on bypass the load does not have UPS protection, and on some UPS the batteries are not available either, so the window is planned.

Is a load bank test the same as a battery test?

No. The load bank test proves the UPS power train at known load steps; its battery discharge lasts minutes. Battery runtime needs a capacity test, run to the battery maker's procedure.

Can the test be done without an external load bank?

On some large UPS, yes. Vertiv's safe capacity test on the Liebert Trinergy Cube and EXL S1 circulates power inside the UPS, so no load bank is connected to the output.

Sources, checked 2026-10-04:

Need a UPS serviced, tested or replaced?

Tell us the site, the UPS and the timing. We reply and quote within 4 business hours, or call 1 (438) 800-0382

Get a quote in 4 business hours
Call 1 (438) 800-0382Get a quote