Load bank testing
UPS load bank testing
A load bank test puts a controlled, measured load on a UPS so you can see how it holds its output at known load steps and through transfers, while the protected equipment stays on a separate path.

Equipment illustration
Key facts
- What it validates:
- That the UPS can meet its own specification, as a check of the whole system's operating performance Vertiv
- Load steps in a published UPS method:
- 50% load for one hour, then 100% load for 3 hours Eaton
- Battery check inside the test:
- A battery discharge of up to 4 minutes, started by opening the rectifier input Eaton
- Where the critical load sits:
- On maintenance bypass, with the load bank connected to the UPS output Eaton
- Readings during the test:
- Infrared scan of UPS and battery cabinets; voltage, current and harmonic content at the output Eaton
- The report:
- Documents the test results Eaton
What the test proves
A load bank test proves that the UPS power train carries a known, steady load at each step and keeps its output in order while it does. Vertiv describes load bank tests as the usual way to confirm that a UPS meets its own specification and operates correctly as a system. Rectifier, inverter, static switch, contactors, busbars and connections all run warm at full load, which is when a weak joint or a worn component shows itself.
ASCO's load bank paper gives the reason for testing: the major reason a generator or UPS fails to perform is inadequate or improper maintenance, and after maintenance or repairs a load bank verifies the design and functional capability of the power system.
The test sequence
The critical load is moved off the UPS first, then the load bank is connected to the UPS output and the load is applied in steps. In Eaton's published method for UPS load bank testing, the load goes to maintenance bypass, the UPS modules are shut down and locked out, an electrician connects the load bank to the output, and the UPS is restarted before any test load is applied. The load then runs at 50% for one hour and at 100% for 3 hours, with voltage, current and regulation watched throughout.
A short battery discharge follows (Eaton recommends up to 4 minutes, by opening the rectifier input), the batteries recharge, and the UPS is transferred to bypass and back several times before the load bank is removed and the critical load returns to normal. The full sequence, with what is recorded at each stage, is on the procedure and requirements page.
Stages of a UPS load bank test
- StageCritical load moved to maintenance bypass; UPS modules shut down and locked out
- StageLoad bank connected to the UPS output, UPS restarted
- StageTest load applied in steps, with voltage, current and regulation watched
- StageShort battery discharge, then recharge
- StageTransfers to bypass and back, load bank removed, critical load returned to normal
When to schedule a test
- At acceptance or commissioning of a new or relocated UPS, before it carries the critical load, and in the integrated systems test that proves a new site as a whole.
- After a repair or a major maintenance job, such as a capacitor, fan or power-module replacement, to prove the work under load.
- Before a change that will lean on the UPS, such as a load increase, a generator change or a planned utility outage.
- As part of a maintenance programme, when the UPS seldom runs near its rating and nobody has seen it carry full load.
ASCO calls a load bank the best practical means of proving a power system without interrupting critical loads.
What the report should show
The report should let someone who was not on site see what was tested, how, and what was found. Eaton's scope states that a report is provided documenting the results; its performance-test scope adds thermal and power-quality readings. Look for:
- The load steps applied, their duration and the measured kW at each step.
- Output voltage, current and regulation at each step, with any abnormality noted.
- Infrared findings for the UPS and battery cabinets: hot spots, with the actual temperatures recorded.
- Power-quality readings at the output: voltages, currents and harmonic content.
- UPS parameters during the battery discharge, and the recharge.
- The transfers to bypass and back, and whether each was clean.
- Findings, open items and recommendations, with photos of anything that needs work.
Report layout, example
| Step | % load | Duration | V | A | Hz | °C |
|---|---|---|---|---|---|---|
Report layout, example. Values are recorded on site.
Limits of the test
A load bank test does not prove battery runtime. The battery discharge inside a UPS load bank test lasts minutes, enough to show that the batteries pick up the load and that the UPS behaves while they do, but not how long they would carry it. Runtime is proven by a battery capacity test, for which battery makers point to the IEEE procedure, and tracked between tests with internal ohmic readings. See UPS and battery load bank testing for how the two fit together.
Nor does it test the distribution downstream of the UPS, or the generator. During the test the critical load runs on bypass, and on some UPS the batteries are not available while the unit is in maintenance bypass, as Schneider Electric notes for the Galaxy VS. The test window is therefore a period of reduced protection and is planned as one.
Testing without an external load bank
Some large UPS can be tested without an external load bank. Vertiv's safe capacity test on the Liebert Trinergy Cube and Liebert EXL S1 circulates power from the inverter back to the rectifier through the static bypass, so the power train is loaded without a load bank on the output. Vertiv states that with double-conversion efficiency above 96%, less than 4% of the circulating power is dissipated, and the test can run up to an overload of 120%. Its battery discharge mode back-feeds the utility, which the site must accept first.
The test plan
Every test follows a written method agreed before anyone arrives. The test plan sets whether the site's electrical infrastructure can carry the critical load and the test load at the same time, the bypass sequence, where the load bank and its cables go and where the heat is rejected, who signs off each step, and what happens if a reading is out of range. The report includes the load steps, the readings and the findings, written for whoever owns the UPS.
In this section
What is a load bank?
Types, ratings, sizes and what each one tests.
How does a generator load bank test work?
Monthly and annual load rules, wet stacking and the method.
Resistive vs reactive load banks
Unity versus lagging or leading load, and when each matters.
UPS and battery load bank testing
Power-train test versus battery runtime, and how to plan both.
Load bank test procedure and requirements
Site requirements and the step-by-step method.
A load bank test
Prepare a service request
Scope to confirm
Connection point, load steps, hold times, transfers and recorded output readings.
Have ready, if known
UPS rating, single-line diagram, bypass arrangement and test window.
Send what you know. The equipment and access details can be confirmed after the first contact.
Questions
How long does a UPS load bank test take?
In Eaton's published UPS method the load runs at 50% for one hour and at 100% for 3 hours, followed by a short battery discharge, recharge and repeated transfers. Add the time to move the load to bypass, connect and remove the load bank, so plan a working day.
Does the critical load stay powered during the test?
Yes, on the bypass path. The UPS is taken out of the load path and the load bank is connected to its output, so the test load never reaches the protected equipment. While on bypass the load does not have UPS protection, and on some UPS the batteries are not available either, so the window is planned.
Is a load bank test the same as a battery test?
No. The load bank test proves the UPS power train at known load steps; its battery discharge lasts minutes. Battery runtime needs a capacity test, run to the battery maker's procedure.
Can the test be done without an external load bank?
On some large UPS, yes. Vertiv's safe capacity test on the Liebert Trinergy Cube and EXL S1 circulates power inside the UPS, so no load bank is connected to the output.
Sources, checked 2026-10-04:
- White paper Vertiv, Safe capacity test: Innovation and savings (white paper SL-70855, R09/22), p. 3-7
- Reference Eaton, Load Bank Testing Scope of Work, Attachment L-6 (revised 5/12/2015), p. 1
- Reference Eaton, Performance Testing Scope of Work, Attachment L-5 (revised 5/12/2015), p. 1-2
- White paper ASCO Power Technologies, Load Banks for Power System Testing (white paper, 2017), p. 2-6
- Manual Schneider Electric, Galaxy VS UPS operation manual 990-5910G, p. 16
- Manual EnerSys, VRLA battery systems safety, storage, operating and maintenance manual US-VR-OM-002 (March 2008), p. 6-35