Monitoring
PUE (power usage effectiveness) explained
PUE, power usage effectiveness, is the total energy a data centre uses divided by the energy that reaches its IT equipment. A PUE of 1.0 would mean every kilowatt-hour goes to IT; anything above that is the overhead of cooling, power conversion, lighting and losses. The UPS sits in the middle of that overhead and is usually where measurement starts.
Need the UPS in this room serviced? Get a quote
On this page
Key facts
- Formula:
- Total facility energy divided by IT equipment energy The Green Grid
- Range:
- From 1.0 to infinity; 1.0 would mean all energy is used by IT equipment The Green Grid
- Inverse:
- DCiE: IT equipment energy divided by total facility energy The Green Grid
- Level 1 (basic):
- IT load read at the UPS output, monthly or weekly The Green Grid
- Level 3 (advanced):
- IT load read at each piece of IT equipment, continuously (15 minutes or less)
- Worked example:
- 600 MWh delivered, 475 MWh to IT: PUE 1.26 The Green Grid
Calculate PUE from energy readings
Use the same measurement period and boundary for both readings.
Enter positive energy readings. Facility energy must be at least IT energy.
How this is calculated
PUE = total facility energy ÷ IT equipment energy. The initial values use The Green Grid's worked example: 600 MWh ÷ 475 MWh = 1.26. A room or container boundary produces partial PUE, which must not be compared with whole-facility PUE.
The Green Grid, White Paper 49
What is PUE?
Short answer
PUE is the ratio of the total energy a data centre facility uses to the energy used by its IT equipment. The Green Grid, which defined the metric, states that PUE for a dedicated building is the total facility energy divided by the IT equipment energy. Total facility energy is everything measured at the utility meter for the data centre: the IT equipment itself, plus the power delivery chain (UPS systems, switchgear, generators, PDUs, batteries and distribution losses), plus cooling, lighting and the rest of the support load.
The result reads as a multiplier: in The Green Grid's illustration, a PUE of 3.0 means the data centre uses three times as much energy as its IT equipment alone. A value approaching 1.0 would mean almost all energy reaches IT. Its inverse, DCiE (data centre infrastructure efficiency), divides IT energy by total energy; the two say the same thing in different forms.
Calculating PUE: a worked example
PUE is calculated from energy over a period, in kilowatt-hours or megawatt-hours, not from a single power reading. The Green Grid explains why: energy is power multiplied by the time it is applied, so a figure built from energy reflects the whole period rather than one moment. The Green Grid's example, from White Paper 49, is a containerised data centre with a UPS that is 95% efficient, a transformer that is approximately 96% efficient, and a chiller outside the container.
| Where the energy goes (one year) | Energy (MWh) | Counted as |
|---|---|---|
| Transformer losses | 25 | Facility overhead |
| Chiller | 75 | Facility overhead |
| UPS losses | 25 | Facility overhead |
| IT equipment | 475 | IT equipment energy |
| Total delivered to the transformer | 600 | Total facility energy |
PUE is therefore 600 divided by 475, or 1.26. The UPS on its own wastes as much energy in this example as the transformer does, which is why UPS efficiency and UPS load level show up in PUE. Drawing the boundary around the container only gives (25 + 475) / 475 = 1.05. The Green Grid calls that a partial PUE and warns that a quoted figure of 1.05 or similar is often the partial PUE of one zone, not the PUE of the whole facility.
Where the IT load is measured
The IT load is read at one of three points, and the point sets the level of the result. The Green Grid defines:
- Level 1, basic: the IT load is read at the UPS output, from the UPS front panel, a meter on the UPS output, or one meter on the common output bus of several UPS modules. Measured monthly or weekly.
- Level 2, intermediate: the IT load is read at the output of the PDUs in the data centre. Measured daily or hourly.
- Level 3, advanced: the IT load is read at each piece of IT equipment, by metered rack PDUs or by the device itself. Measured continuously, every 15 minutes or less.
Total facility energy is measured at the utility input at every level. Moving from Level 1 to Level 2 takes the losses of the PDUs and their transformers out of the IT figure and puts them where they belong, in the overhead. ASHRAE's paper on power equipment notes that many PDUs already have built-in power monitoring whose data can be used to calculate PUE, so Level 2 is often a matter of collecting what the equipment already reads.
What PUE does not show
A PUE figure does not show how much useful work the IT equipment does, and it can move the wrong way after a good decision. The Green Grid gives the example of virtualisation: virtualising servers can reduce the total IT load and still raise PUE, because the cooling and power overhead does not fall in proportion. The facility uses less energy overall, yet the ratio looks worse.
PUE also depends on when and how it is measured. The Green Grid recommends taking Level 1 and Level 2 readings at about the same time of day, when the load is as consistent as possible with earlier readings, and keeping the day of the week constant for week-to-week comparisons. Comparing your PUE with another site's makes sense only when both use the same level, the same period and the same boundary; a container's partial PUE and a building's PUE are not the same number.
Meters for PUE
PUE needs two energy measurements at minimum: total facility energy at the utility input, and IT equipment energy at the chosen level. The Green Grid asks for a kilowatt-hour meter that reports true energy, by measuring voltage, current and power factor together over time, rather than a current reading multiplied by an assumed voltage. In many sites the UPS display or its network card is the first IT meter available; Lawrence Berkeley National Laboratory's guide on energy information systems notes that points not metered automatically are often recorded by hand from equipment displays such as the UPS display.
Monitoring software collects those readings automatically; see DCIM vs BMS for the difference between a DCIM platform and a building management system for this job, and the server room monitoring guide for the sensors around the same racks.
The UPS and PUE
A UPS lowers PUE by wasting less energy between its input and its output. In the worked example the UPS losses equal the transformer losses, so a more efficient UPS, or one running at a better point on its efficiency curve, cuts overhead directly. Efficiency depends on the UPS design, its operating mode and how heavily it is loaded; see the data centre power architecture guide for where the UPS sits in the power path. When an older UPS is due for replacement, include efficiency at the real load in the comparison; for APC Galaxy frames, APC Galaxy UPS maintenance and service covers the maintenance side of that decision.
Questions
What is a good PUE?
Lower is better, and 1.0 is the floor. There is no single target: the figure depends on climate, cooling design, redundancy and load. Compare your own PUE over time, at the same measurement level, before comparing it with other sites.
Is PUE measured in power or energy?
In energy. The Green Grid's examples use energy over a period, such as a year in megawatt-hours, because power is only a snapshot of one moment.
Does the UPS count as IT load or overhead?
Overhead. UPS systems, switchgear, PDUs, batteries and distribution losses are all part of total facility energy. At Level 1 the IT load is read at the UPS output, after the UPS losses.
Why did my PUE go up after virtualisation?
Because the IT load fell faster than the cooling and power overhead. The Green Grid gives this as an example: total energy can drop while the ratio rises.
What is partial PUE?
PUE calculated for one zone, such as a container or a room, rather than the whole facility. In the Green Grid's example the container's partial PUE is 1.05 while the facility's PUE is 1.26.
Sources, checked 2026-10-04:
- White paper The Green Grid, White Paper #49: PUE, A Comprehensive Examination of the Metric (2012), p. 8-34
- White paper The Green Grid, White Paper #49, partial PUE usage example 1 (Figure 17), p. 65
- White paper ASHRAE TC 9.9, Data Center Power Equipment Thermal Guidelines and Best Practices (white paper, 2016), p. 10-38
- Reference Lawrence Berkeley National Laboratory, Guidelines for Datacenter Energy Information Systems, LBNL-6935E (2013), p. 16-45
Need the UPS in this room serviced?
UPS service: reply and quote within 4 business hours; same day in Montreal, Quebec City, Toronto and Ottawa; 24 to 48 hours elsewhere. 1 (438) 800-0382